TeraWulf Secures Google Credit Support for Its $19 Billion Anthropic Campus and Signs Fluor to Build It

TeraWulf Inc. (NASDAQ: WULF), a developer and operator of power-backed data center campuses for AI and high-performance computing, announced on November 4, 2026 that it has executed credit support agreements with Google LLC. The agreements back the debt financing for its Justified Data Campus in Hawesville, Kentucky, where Anthropic has signed leases worth about $19 billion. At the same time, TeraWulf signed a definitive engineering, procurement and construction (EPC) agreement with Fluor Enterprises to build the campus.

How the Google Credit Support Works

Under the new agreements, Google provides contractual credit support for the debt TeraWulf expects to raise for the Justified buildout. Google is a subsidiary of Alphabet, whose senior unsecured debt carries ratings of AA+ from S&P Global Ratings and Aa2 from Moody’s. As a result, the anticipated project debt carries contractual support from a company with investment-grade credit.

Above all, management framed the deal around the cost of borrowing. “Cost of capital is fundamental to infrastructure development,” said Patrick Fleury, Chief Financial Officer of TeraWulf. He added that strong investment-grade credit support strengthens the project’s financing profile and the company’s ability to pursue competitive long-term debt.

The structure follows a plan TeraWulf outlined from the start. When it announced the 20-year Anthropic lease in July, the company said it expected an investment-grade credit to support the lease. Google has also backed TeraWulf’s tenants before. In the second quarter of 2026, the delivery of a building at the company’s Lake Mariner campus in New York made $600 million of Google’s credit support for Fluidstack’s lease obligations effective.

Fluor Takes On Construction at Justified

The Fluor agreement covers engineering, procurement and construction for three data center buildings at Justified. It builds on the limited notice to proceed that TeraWulf announced in March 2026. As a result, Fluor’s role now extends from early engineering and preconstruction to the full scope of work, including testing and commissioning.

In particular, the contract sets defined delivery milestones, open-book cost reporting, procurement oversight and contractual performance protections. Pricing follows a guaranteed maximum price (GMP) model, and the companies will set that price as engineering and procurement progress. Under the milestone schedule, TeraWulf expects phased ready-for-service completions to begin in late 2027 and continue through the second quarter of 2028. By comparison, the July lease announcement targeted initial capacity in the second half of 2027 and the full 401 MW of critical IT load by early 2028.

TeraWulf also pointed to labor as one reason for bringing in Fluor. The company noted that labor availability has become an increasingly important constraint on large data center projects. “Fluor gives us the ability to scale execution without building a global engineering and construction organization internally,” said Paul Prager, Chairman and Chief Executive Officer of TeraWulf.

Funding a Multi-Campus Buildout

Justified is one of several large projects TeraWulf is financing at once. At the end of the second quarter, the company held about $3.0 billion of cash and restricted cash. During that quarter, it generated $44.8 million in revenue, and HPC lease revenue made up about 71% of the total. In addition, TeraWulf reached 102 MW of revenue-generating critical IT capacity at Lake Mariner in early July, with another 336 MW under construction there.

The Kentucky pipeline adds to those capital needs. In August, the Kentucky Public Service Commission approved a power agreement for up to 482 MW of electric service at Justified. Then, in October, TeraWulf expanded contracted power capacity at its separate Muskie Data Campus in eastern Kentucky from 500 MW to 1 GW. Against that backdrop, the Google backstop gives TeraWulf investment-grade support for financing the Justified lease.

Investors will get more detail soon. TeraWulf plans to report its third quarter 2026 results on Friday, November 6, before an earnings call at 8:00 a.m. ET. “What gives us confidence is what we have in the ground, what we have under contract, the investment-grade credit supporting those commitments and a team with decades of experience delivering large-scale infrastructure,” Prager said.

Strategic Investment Summary

  • Credit Backstop: TeraWulf (NASDAQ: WULF) executed credit support agreements with Google on November 4, 2026 for debt financing at its Justified Data Campus in Kentucky.
  • Contracted Revenue: The campus supports about $19 billion of contracted lease commitments with Anthropic over a 20-year initial term.
  • Investment-Grade Support: Alphabet’s senior unsecured debt carries AA+ and Aa2 ratings from S&P and Moody’s.
  • Construction Partner: Fluor signed a definitive EPC agreement covering three data center buildings, with guaranteed maximum pricing set as work progresses.
  • Delivery Schedule: TeraWulf expects phased ready-for-service completions from late 2027 through the second quarter of 2028.
  • Upcoming Results: The company will report third quarter 2026 results on November 6, after ending the second quarter with about $3.0 billion of cash and restricted cash.

Find out more about the latest corporate developments and financial reports at the TeraWulf investor portal.

Share this article:

About the Author:

Organigram to Acquire Aurora for C$7.80 per Share, Topping Curaleaf’s Hostile Bid

Victoria Lambe

PRISM Market View Alerts

Get your dose of PRISM Market
View news, right in your inbox

Mailchimp Signup